The main structure of MGM Dubai, the three-hotel resort rising on a man-made island beside Burj Al Arab, has reached its full height, developer Wasl Group announced on Monday, November 16. The project is now scheduled to open in early 2029.
Structural topping-out marks the point at which a building’s frame is complete. Façade, building systems and interior fit-out work normally follow before a hotel can receive guests.
What is being built
The resort sits on an artificial island of about three million square feet off the Umm Suqeim and Jumeirah coastline. It will bring together three hotel brands from MGM Resorts International, namely MGM, Bellagio and ARIA, with a combined 1,500 rooms.
Plans also include around 40 dining venues, a beach club, a theatre, and retail, wellness and entertainment facilities. Senior representatives of Wasl Group, MGM Resorts and the main contractor, China State Construction Engineering Corporation (CSCEC), attended a ceremony to mark the milestone, Retail & Leisure International reported.
Hesham Al Qassim, Group Chief Executive Officer of Wasl Group, said the milestone supports Dubai’s long-term vision and strengthens its position as an international destination, according to the same report.
Al Qassim told the Arabic daily Al Bayan that the project is about 68 per cent complete and will cost around Dh10 billion, EnterpriseAM reported. Neither figure appeared in the other announcements reviewed for this article.
A later opening date
The early 2029 target is roughly a year later than the March 2028 date MGM Resorts chief executive Bill Hornbuckle gave investors in February, according to travel industry publication Skift. It is the second change in about 18 months, after earlier guidance for the third quarter of 2027.
The announcement did not explain why the date had moved, Skift noted. Ari Kastrati, MGM Resorts’ chief content, hospitality and development officer, said the partners were committed to “keeping this momentum going” as the project heads towards opening.
The revision comes at a time of higher building costs in the emirate. Dubai’s construction cost index rose 11.64 per cent year on year in July, according to property consultancy Cavendish Maxwell, as cited by EnterpriseAM. Neither Wasl nor MGM has linked the new timeline to costs.
What it means for Dubai’s hospitality market
Once open, the resort would add 1,500 rooms in one of Dubai’s best-known beachfront districts, next to Burj Al Arab and the Jumeirah coastline. Its mix of three hotel brands, dozens of restaurants, a theatre and a beach club places it in the large integrated-resort category rather than a single hotel.
For businesses in Dubai’s construction and hospitality supply chain, the topping-out signals a shift from structural work to the fit-out phase, which typically involves interiors, mechanical and electrical systems, and specialist suppliers. For residents and visitors, the practical takeaway is that the resort remains more than two years from opening; the announcements covered here did not include booking dates or room rates.
Key facts
- Developer: Wasl Group, with MGM Resorts International as hotel partner
- Main contractor: China State Construction Engineering Corporation (CSCEC)
- Location: artificial island of about 3 million sq ft near Burj Al Arab
- Hotels: MGM, Bellagio and ARIA, 1,500 rooms in total
- Facilities: about 40 dining venues, a beach club, a theatre, retail and wellness
- Milestone: structural topping-out announced on November 16, 2026
- Opening target: early 2029 (previously March 2028, and before that Q3 2027)
Sources: Skift, Retail & Leisure International, EnterpriseAM